The board swap itself is predictable. What is not predictable is what testing the installation turns up. Quote the predictable part as one fixed price that includes testing, the certificate and the notification. Then list the faults you think you might find as separate priced lines, each one going ahead only when the customer has said yes. A customer who has seen the possible extras in writing before you start is less likely to argue about them afterwards.
Look before you price
A consumer unit quote given over the phone is a guess. A short visit lets you see the existing board, how many circuits it feeds, the earthing and bonding arrangements you can see, and any signs of older wiring. It also lets you tell the customer, face to face, that testing can turn things up and that you will price anything you find before you do it.
Write down what you saw. If the quote later says "bonding to the gas supply not visible at survey", you both know where that line came from.
The fixed part of the quote
| Line | What it covers |
|---|---|
| Consumer unit | The make, the number of ways and the protective devices, so the customer can compare like with like |
| Fit and connect | Removing the old board and connecting the existing circuits to the new one |
| Testing and certification | Testing every circuit, and the Electrical Installation Certificate |
| Building Regulations notification | Notifying the work through your competent person scheme, or the building control fee if you are not registered |
| Power off | Roughly how long the house will be without power, and when |
| Surge protection | Included, or the reason it is not |
Putting testing, certificates and notification on as named lines matters when a customer compares your price with a lower one. A quote that leaves them out is not cheaper, it is unfinished.
The lines that depend on the survey or testing
Some of these show up at the survey, or with a quick test while you are there. Others only show once the board is out and every circuit is tested. Price each one on its own, so the customer can see what each would cost before it is needed.
| Possible line | How to price it |
|---|---|
| Main bonding to water or gas | A fixed price for each, if it is missing or undersized |
| A circuit that fails test | Your hourly or day rate to trace and repair, with an estimate of hours |
| Damaged or unsafe accessories | A price per accessory replaced |
| Relocating the board | A fixed price, if the current position cannot be kept |
| Isolation | A fixed price to fit an isolator, with any network operator charge for isolation passed on at cost, if the supply cannot otherwise be made dead |
| Meter tails | A fixed price to replace them, if they are undersized or in poor condition |
| Earthing | A fixed price for an earth electrode or other earthing upgrade, if the existing earthing is unsatisfactory |
Say on the quote what happens when one of these comes up: you stop, explain what you found, and confirm the price in writing (a text or email is enough) before carrying on. If a circuit cannot be made safe that day, say what you will do with it, so the customer is not surprised to find something left disconnected.
Notification and certificates
In England, installing a new consumer unit is notifiable work under the Building Regulations, according to the Planning Portal's guidance on electrics, checked on 16 November 2026. The same guidance says:
- An electrician registered with a competent person scheme can self-certify the work. They give the homeowner an Electrical Installation Certificate, and the homeowner should get a Building Regulations Compliance Certificate within 30 days.
- If you are not registered, the building control body or a registered third-party certifier has to be notified before the work starts.
Wales, Scotland and Northern Ireland have their own rules. Telling the customer on the quote that both certificates are coming, and roughly when, saves a phone call a month later asking where the second one is.
When the job is booked from the customer's home
If you agree the job with a homeowner while you are at their house, they have a right to cancel under the Consumer Contracts Regulations, and when the 14 days start depends on the kind of contract. For a labour-only job, regulation 36, checked on 16 November 2026, says you must not start within the cancellation period unless the customer has expressly asked you to, and for a job agreed in their home that request has to be on a durable medium, such as an email or a signed form. If you supply the board as well as fit it, the contract may count as a sales contract, with different timing. The guide to deposits and payment schedules sets out both cases. A consumer unit swap is often booked within days, so it is worth having the wording ready.
Where software helps
A quote with optional lines is easier to send from software that lets the customer accept the main price and tick the extras they agree to, and if your tool lets you attach files to a job, the certificates stay with the invoice. Check that the tool you use supports optional quote lines before relying on it. Our software list shows which tools say they do.
Before your next board change
- Visit before you price, and write down what you saw.
- Put testing, certificates and notification on the quote as named lines.
- Add priced lines for the faults you are most likely to find, each marked "only if needed and agreed".
- Say on the quote what happens when testing finds something, and how you will confirm the extra.
- Have the cancellation information and the "start early" request wording ready for jobs booked at the customer's home.