A mowing round works when each day covers one area, the order within each day stays the same week to week, and there is a gap somewhere in the week to catch up after rain. Set those up before the season, along with a rule for rain, and most weeks run themselves. Leave them to chance and one wet Tuesday pushes the whole round out of shape for weeks.

Put every customer on a map

Start with where your customers are, not with which day they asked for. Drop a pin for each address on a map. A free online map with coloured pins, one colour per day, makes clusters and stragglers easy to spot.

What you are looking for is natural groups: a village, an estate, one side of town. Each group becomes a day, or half a day.

Build each day around one area

Once the groups are clear, give each one a day and keep to it. Within the day, fix the order so you drive a loop rather than criss-crossing. Customers like knowing they are "Tuesday mornings", and you stop thinking about the route.

Watch for the outlier. A single customer 20 minutes from everyone else costs you 40 minutes of driving for one lawn. Either price that visit to cover the drive, move them to a day when you are nearer, or let them go.

Balance fortnightly customers

Fortnightly customers can make one week heavy and the next light. Split them into week A and week B, and put roughly the same amount of work in each. When a new fortnightly customer signs up, add them to whichever week in their area is lighter.

Leave a slack slot

Keep spare time each week: half a day for most of the year, Friday afternoon for example, and a full day at the height of the growing season. In a dry week it takes one-off jobs: a hedge, a clearance, a quote visit. In a wet week it is where the lost lawns go. Half a day of slack absorbs half a lost day; a whole day washed out needs the full day, or the skip rule below. Without any slack, rain pushes every later day back and you stay behind.

Decide your rain rule now

Before the season, decide what happens when you cannot mow, and tell customers in writing. The two common rules are:

  • Push the whole day. Tuesday moves to Wednesday, and everything after it shifts towards the slack slot. Customers get every cut, a day late, as long as there is enough slack to absorb it.
  • Skip the cut. Tuesday's customers miss a week and you pick them up on the next round. This only works if your billing deals with it.

Which rule you choose decides how you bill. If customers pay per cut, a skipped cut is simply not charged. If they pay a fixed monthly amount, say in the terms how many cuts the month covers, and what happens to cuts lost to weather.

Moving the round off paper

On paper, moving a wet Tuesday means rewriting every day after it. Scheduling software that handles recurring visits holds each customer's day and frequency once. When comparing tools, check whether one can move a whole day's visits at once and tell the customers affected. The guide to what job management software does covers what to look for. The method above still comes first: software will not fix a round whose days are badly drawn.

Plan for the season changing

Growth slows in autumn and the round shrinks. Some weekly customers will want to drop to fortnightly. Agree that change at the start of the season, so it is not a negotiation on every doorstep in September. The same goes for the first cut of spring.

This week

The quiet months are the time to redraw a round.

  1. Pin every customer on a map this week and colour them by their current day.
  2. Redraw the days around areas, with fortnightly customers split into week A and week B.
  3. Decide how much slack you will keep, and when it goes up to a full day.
  4. Write down your rain rule and how it affects billing, ready to send with next season's terms.